The prolonged drought during summer and fall has depleted the water reserves of Albanian hydroelectric power plants, forcing the Albanian Power Corporation to purchase large amounts of electricity from imports at prices reaching up to 366 euros per megawatt-hour.
The lack of rainfall and the drop in flows in the Drin cascade have limited domestic production capacity, while November’s rains have begun to improve the water situation after months of low reservoir levels. But this appears to be insufficient.
Under these conditions, KESH has been forced to secure energy on international markets, incurring a heavy financial burden.

According to the official results of the auctions published by the corporation itself, for the period November 2-15, 2026 alone, KESH has contracted 145,680 MWh of electricity, with an estimated value of around 48.7 million euros.
In the first procedure, for 77,616 MWh of energy, the average purchase price reached €338.44/MWh, while another 13,944 MWh were contracted at €326.79/MWh.
The situation worsened in the procedure for the November 4–8 supply, when KESH purchased 24,000 MWh at an average price of €351.33 per MWh and another 7,470 MWh at €364.90 per MWh.
In this procedure, the highest contracted price reached €366/MWh.
Even in the latest published purchase, for the period November 11–15, the corporation contracted 21,600 MWh of energy at an average price of €297.64 per MWh, spending about another €6.43 million.
But while KESH is paying millions of euros for imports, the Turkish joint-venture company AYEN Energji AS has failed to deliver 59 million kWh of energy to the Albanian state, which it is obligated to supply under the contract.
This company exploits Albanian water resources through three hydroelectric power plants on the Fan i Madh and Fan i Vogël rivers, with an installed capacity of 109 MW.

According to the concession contract, AYEN is obligated to deliver to the Albanian state free of charge 2.1% of the energy it produces each year.
But the company’s financial documentation, previously reviewed by skyweb.al, shows that this obligation has not been fulfilled since 2014. The accumulated amount of undelivered energy has reached 59,047 MWh, or over 59 million kilowatt-hours.
AYEN Energji AS is selling the energy it owes the state itself.
The financial dimensions of this obligation become even more apparent when compared to the prices at which KESH is buying energy from abroad.
If 59,047 MWh were valued at the average price of €297.64 per MWh from the most recently published purchase, their economic value would amount to about €17.6 million. Meanwhile, at the €364.90/MWh price recorded in early November, this amount of energy would have a value of around €21.5 million.

In fact, the AYEN AS Energji contract also provides for the possibility of paying the concession fee in cash, according to the specified conditions, but this form of payment has also not been carried out.
In its 2025 financial statements, the company acknowledges the failure to deliver the energy it owes the state, arguing that the methodologies and delivery conditions have not yet been defined.
Skyweb.al learns that despite the obligation accumulated for more than a decade, AYEN has not recorded any financial provisions for this matter, while the energy the Turks owe the Albanian state has so far been sold on the open market by them, also profiting extra from the high prices.
10 million euros in profit
Meanwhile, the company’s operations in Albania remain highly profitable.
In 2025 alone, AYEN AS Energji realized a net profit of approximately 1.04 billion lek, while a year earlier the profit had reached about 1.21 billion lek. /skyweb.al